Contractor suspends work on Lagos-lbadan Expressway over debt

Rate this item
(0 votes)

Contractor handling the reconstruction and expansion works on the Lagos-Ibadan dual carriageway, Section II, along Shagamu-Ibadan, with Contract No. 6205, has suspended further execution of the project due to a total outstanding debt of N8.94bn.

 

Reynolds Construction Company Nigeria Limited, in a letter addressed to Minister of Power, Works and Housing, Mr. Babatunde Fashola, and dated June 2, 2017, called the attention of the minister to the worsening financial situation of the project and pleaded for his intervention in order to ease the continuation of work on the site.

 

The letter which was received and acknowledged by the office of the minister on June 5, 2017, and made available to our correspondent in Abuja on Friday, revealed that as of when it was sent, the outstanding debt on approved certificates for certified works on the project was N7.83bn.

 

Reynolds told the minister that the 28-day window allowed for the payment of the certificates as contained in the conditions of the contract between parties had “long expired.”

 

The firm said, “In addition, there is another Certificate (No.19) of N1,108 334,258 under processing. Thus, making a total of N8, 937,611,552. The mounting debt profile on this project is worrisome.”

 

The letter, which was signed by the firm’s Managing Director, who simply gave his name as M. Nakhla, stated that RCC was committed to the successful completion of the project, but maintained that funding was a challenge.

 

It said, “In view of the dire situation, we shall be constrained to suspend further execution of work unless there is an appreciable improvement in the project’s cash flow and adequate funding arrangement is put in place for further works. This painful decision is bound to delay the scheduled completion of the project, in addition to the inherent cost implication.

 

“This letter is, therefore, a notice of our intention to suspend further execution of the project, pursuant to Clause 68(8) of the Conditions of Contract. In that unfortunate event, we shall require payment of the outstanding debt as well as full coverage of our attendant expenses and losses before the resumption of work. A corresponding extension of time shall also become imperative, pursuant to Clause 44 of the CC.”

 

Punch 

November 23, 2024

NNPC not delivering quantity of crude oil agreed on, Dangote refinery says

The federal government's plan to sell crude priced in the local currency is faltering, with…
November 24, 2024

PDP governors urge Tinubu to review economic policies amid rising hardship

Governors elected on the platform of the Peoples Democratic Party (PDP) have called on President…
November 24, 2024

Older adults opened up about things they ‘took for granted’ in their 20s and 30s

Last month, we wrote a post where older adults from the BuzzFeed Community shared things…
November 16, 2024

Influencer eats pig feed in extreme attempt to save money

Popular Douyin streamer Kong Yufeng recently sparked controversy in China by eating pig feed on…
November 22, 2024

FG excited as pro-Biafra agitator Simon Ekpa arrested in Finland on terrorism charges

Simon Ekpa, the controversial leader of the pro-Biafra faction Autopilot, was arrested by Finnish authorities…
November 24, 2024

What to know after Day 1004 of Russia-Ukraine war

WESTERN PERSPECTIVE Putin signs law forgiving debt arrears for new Russian recruits for Ukraine war…
November 21, 2024

Nigeria comes top in instant payment system inclusivity index in Africa

Nigeria’s instant payment system is projected to advance to the maturity inclusion spectrum ahead of…
October 27, 2024

Nigeria awarded 3-0 win over Libya after airport fiasco

Nigeria have been awarded a 3-0 victory over Libya, and three vital points, from their…

NEWSSCROLL TEAM: 'Sina Kawonise: Publisher/Editor-in-Chief; Prof Wale Are Olaitan: Editorial Consultant; Femi Kawonise: Head, Production & Administration; Afolabi Ajibola: IT Manager;
Contact Us: [email protected] Tel/WhatsApp: +234 811 395 4049

Copyright © 2015 - 2024 NewsScroll. All rights reserved.