Following the perennial power outages currently being experienced across the country; findings have shown that 20 gas power plants are currently under-performing, leading to power generation dropping below 2,000MW.

Nigeria has 23 power generating plants with 11,165MW capacity connected to the national grid. These plants are managed by generation companies (GenCos), independent power providers, and Niger Delta Holding Company. Out of the 23, two are hydro plants.

Independent investigations by The PUNCH showed that the gas plants are currently either generating below expectations, shut down due to lack of gas, or undergoing maintenance.

Investigations further showed that the affected plants included: Omotosho units 5 & 6, Olorunsogo units 3, 4 & 6, Omoku Units 3 & 6, Omotosho NIPP units 3 & 4, Delta units 15, 17, and 18, Afam VI units 11 & 12, Olorunsogo NIPP unit 3, Ihovbor NIPP unit 2, Sapele Steam unit 3, Sapele NIPP unit 1, Odukpani NIPP units 1 & 3, and Okpai units 11, 12 & 18.

Also, Jebba Hydro and Shiroro power generating stations are either out or have limited generation capacity.

Other affected power generating plants include: Omotosho units 3&4, Olorunsogo unit 1, Delta units 10 &20, Afam VI unit 13, Ihovbor NIPP unit 4, Geregu NIPP units 22&23 and Odukpani NIPP units 2, 4 & 5. These are out either because of fault or for scheduled maintenance.

The two hydro plants, Shiroro and Jebba, are also experiencing generation shortfall due to water management.

Further checks revealed that there were fault and technical problems in the country’s largest gas plant, Egbin, which took it completely off the grid, causing 514MW shortfall. 

In Geregu, the situation caused 230MW shortfall, with reported fault at Alaoji NIPP. Olorunsogo, Omotosho, Sapele NIPP, Omotosho NIPP, Omoku, Okpai, Afam VI, Olorunsogo NIPP, Geregu NIPP, and Ihovbor are also experiencing different constraints currently weighing down their performances.

Odukpani NIPP, which was recently shut down due to gas pipeline pigging, is also yet to fully bounce back to full generation capacity.

However, 16 gas plants were on weekend back on the national grid with Delta Power generating the highest at 332MW.

Also on the grid are: Rivers IPP (160MW), Sapele (53MW), Sapele NIPP (94.90MW), and Shiroro Hydro (122MW).

Power generation was put at 1,936.90 mega watts from 3,647MW last recorded.

Ministry of Power over the weekend confirmed The PUNCH findings when it released a statement apologising to the public over the current dip and stated that there was a partial shutdown of the Oben gas plant to address the repair of critical gas processing equipment.

“The incident, unfortunately, occurred at a time when other power plants on other gas sources are undergoing planned maintenance and capacity testing,” the statement signed by Special Adviser to the Minister of Power, Isa Sanusi, said.

Spokesperson for Eko Electricity Distribution Company, EKEDC, Godwin Idemudia, said the station currently got low allocation from the Transmission Company of Nigeria.

According to Idemudia, as of Saturday, load allocated to it was a mere 240MW out of expected 861MW.

“This affects all our injection substations. For example, Alangbon TS (covers IKoyi, Keffi, Obalende and environs) is expected to be 135 mw but we got 64.4 mega watts. On the overall, instead of getting 861mw, we are given 240.1 mw. We cannot give what we don’t have. The only way out is to load shed so it can go round all our customers,” he said.

The TCN had blamed the situation on a combination of issues ranging from gas constraints, fault, and technical problems within generating plants which caused persistent low generation and consequently low load allocation to distribution companies nationwide.

“This is based on the fact that TCN can only transmit what is being generated by Gencos and presently they are all generating below capacity,” the transmission company stated in a note.

 

Punch

May 02, 2024

Investors on NGX lose N3.57trn on sustained stock sell off in pursuit of higher yields…

In April, the NGX All-Share Index witnessed a significant downturn, shedding N3.57 trillion in market…
May 01, 2024

Overwhelming majority of Nigerians have lost confidence in INEC, survey reveals

Yiaga Africa, a prominent election observation group, reveals in its latest report that only 23…
April 27, 2024

Adults are sharing the things they are no longer interested in now that they're older

It's natural for our preferences to change as we get older. So when asked, "What…
April 13, 2024

A new camera can undress people almost in real time—to send a message about AI

Nuca, a new deepfake camera, is an art project that shows how artificial intelligence can…
May 01, 2024

Gunmen abduct 4 residents in fresh attack on Abuja community

Gunmen struck the Bmuko Community in the Dutse Baupma area of the Bwari Area Council,…
May 02, 2024

What to know after Day 798 of Russia-Ukraine war

RUSSIAN PERSPECTIVE Russia hits Ukrainian military HQ – MOD Russia has carried out a strike…
May 01, 2024

Wellspring Consulting proposes cybersecurity investment to boost Nigeria's economy

In a bid to rescue Nigeria from its economic challenges, Wellspring Consulting advocates for significant…
April 30, 2024

Finidi George is new Head Coach for Super Eagles

Former Nigerian winger Finidi George has been appointed as the head coach of the national…

NEWSSCROLL TEAM: 'Sina Kawonise: Publisher/Editor-in-Chief; Prof Wale Are Olaitan: Editorial Consultant; Femi Kawonise: Head, Production & Administration; Afolabi Ajibola: IT Manager;
Contact Us: [email protected] Tel/WhatsApp: +234 811 395 4049

Copyright © 2015 - 2024 NewsScroll. All rights reserved.